A new wastewater treatment plant built for the Abu Dhabi Tourist Development & Investment Company (TDIC) capacity 98,000m³ per day. Initial appointed by Kharafi National the main contractor to look at disputed variations and delays to the progress of the works. Then the employer TDIC desired to keep the project on schedule despite the fact that the supply of wastewater for treatment was not available due to delays with surrounding urban and residential developments. In an unusual move rather than suspend the works the Client arranged for tanker loads of wastewater to be delivered to the site for processing.
Part of the works were affected by the intermittent supply of waste water and recommendation was made to Kharafi National to appoint further members to the team in the form of a claims writer and delay analyst to identify areas of significant change to the programme that had resulted in delays for which the contractor was entitled to additional time and money.