Laura Palmer
FOUNDER

Providing commercial management and claims preparation services, managing a 14-man team responsible for producing claims for extensions of time and loss and expense This was a new refinery which encountered problems to do with the discovery of ground water, wax and sour gas contaminates all of which had a dramatic effect on the project requirements. The team was able to demonstrate entitlement due to the deficient FEED which the original contract sum had been based upon and was also able to demonstrate entitlement to additional costs for engineering, prolongation, variation and price escalation. A claim document was submitted to the Employer in excess of US$ 400m.